PSA Mumbai Phase II overall project progress is 78% as of December 2024.
Construction of the 1000m wharf is complete. The first batch of container handling equipment, comprising 2 Quay Cranes (QCs) and 6 Rubber-Tyred Gantry Cranes (RTGs), was delivered to the site on November 1st, 2024 10 million safe working man hours been recorded during the Phase II construction up to December 2024.